SALTO Test Campaign:
Themis reusable launcher first stage prototype
conducts a flight chronology rehearsal
On 23 July 2026, the reusable
stage demonstrator Themis conducted a flight
chronology rehearsal at Esrange Space Center in
Sweden. The ArianeGroup and SSC
Space teams have reached a major milestone in
preparing for Europe's first flight test with
recovery, known as the Hop Test. Each milestone
brings ArianeGroup closer to its goal of giving
Europe sovereign capabilities in reusable space
technologies.
This rehearsal, also called wet
dress rehearsal, marks a key milestone in the
development of the launch system, comprising the
Themis demonstrator and the ground infrastructure
deployed at Esrange Space Center in Sweden.
The objective of the test was
to simulate launch operations under cryogenic
conditions, including pre-flight preparation of the
demonstrator and its launch pad, as well as the
system passivation that will be carried out after
post-flight recovery.
The rehearsal was conducted
with liquid nitrogen replacing the propellants,
liquid oxygen and liquid methane, in all cryogenic
lines and tanks, enabling the simulation of
cryogenic temperature and pressure conditions, as
low as -200°C during the test. The chronology
simulation lasted a full day for the duration of the
countdown and the post-virtual-launch activities of
safing the site.
The test has provided essential
data for the continuation of the SALTO project
implementation and test campaign. The teams are now
working to define the window for the next test.
The test campaign in the scope
of the EU-funded project SALTO follows a
test-and-learn approach. It relies on successive
demonstrations to develop and mature the
technologies required for reusability. Each
milestone marks further progress towards reusable
launch technologies in Europe.
|