Spain’s
MIURA 1 launch campaign kicks off
3 October
2023
MIURA 1
launch campaign kicks off. PLD Space has
successfully concluded the two pre-launch tests of
the first flight unit of the Spanish launcher,
specifically the umbilical cable tests and the Wet
Dress Rehearsal (WDR). The positive results obtained
during these tests effectively give the green light
to the flight mission of the suborbital
microlauncher.
The launch
will take place this October at the El Arenosillo
Experimentation Centre (CEDEA) of the National
Institute for Aerospace Technology (INTA) in one of
the different launch windows that PLD Space has
reserved in October and November. The company will
announce this date approximately 24 hours in
advance.
PLD Space is
gearing up for the third launch attempt of MIURA 1.
On 31 May, the company postponed the flight of its
microlauncher due to the winds at altitude, and on
June 17, it tried again, but an automatic abort
occurred just 0.2 seconds prior to lift-off. Since
then, PLD Space has not been able to schedule a new
flight attempt over due to mandatory compliance with
current fire prevention regulations, the high
temperatures at this time of year and its commitment
in conjunction with the Guardia Civil to ensure
safety in the area.
Consequently, the team has spent recent months
meticulously analysing the events of the initial
launch and conducting comprehensive checks to ensure
a successful outcome for the upcoming flight.
The main
conclusion of the analysis conducted confirms that
the automatic abort resulted from the release timing
of the umbilicals (the cables connecting the rocket
to the launchpad). Further insight revealed a mere
one-tenth of a second delay in the release of one of
the umbilicals.
The ground
software interpreted that one of these cables had
not been released and automatically sent a command
to abort the launch. The reality is that this
release had indeed been executed, but with a delay
of 0.1 seconds. Data obtained by PLD Space shows
that this delay was caused by a one-degree deviation
in inclination measured by a strongback sensor.
"If the
cable is less taut than expected, the pull time is
longer because the system only has to pull the
connector but first it has to tension the cable and
so the margin of error was very small," explains PLD
Space Launch Director and Co-founder Raúl Torres.
"The rocket engines function until they’re told not
to and in this case, it was the ground software that
sent the command to not continue with the launch
because it understood that the umbilicals were still
connected”.
With these
conclusions, the Spanish space company has made the
necessary adjustments to the inclinometer and, over
the last few weeks, has undergone a comprehensive
series of tests to ensure the repeatability of the
system. Likewise, the response times of the software
have been adjusted according to the results obtained
during these tests. Simultaneously, PLD Space has
conducted maintenance on every integrated subsystem
of the rocket.