Troubled Defence satellite project
still not off the Projects of Concern list
Defence has not yet removed the
decade-long satellite capability improvement program JP2008
phase 3F from its “Projects of Concern” list – despite
statements to the contrary from its head of capability
acquisition to a Senate Estimates committee hearing
recently. Tenders for JP2008 phase 3F first went out in
2007, with the main work to build a new satellite ground
station in Western Australia and an upgrade to an existing
ground station at HMAS Harman just outside Canberra.
Kim Gillis, deputy secretary of Defence's Capability
Acquisition and Sustainment Group, told the estimates
hearing that the project had been superseded by a newer
project and that it had finalised terms to recover costs
from prime contractor BAE late last year.
“We signed a settlement deed with BAE in November last
year. That was for the completion of the ground base station
west. But we have terminated the east coast requirement. The
terms of the settlement are a full recovery of all those
costs,” he told the hearing, adding: “We consider that one
as having been removed from the Projects of Concern list.”
However, following inquiries from Space & Satellite AU,
Defence denied that it was out of trouble just yet. “At
present JP2008 phase 3F remains on the Projects of concern
list,” a Defence spokesperson told us.
JP2008 phase 3F, part of the Australian Defence Satellite
Communication Capability Terrestrial Enhancement program,
entered the Projects of Concern list back in 2015 due to
cost and time over-runs. When it entered the list it was
already five years behind schedule.
The project is a critical component in providing
communication to Australian troops via the US Wideband
Global Satellite constellation, which Australia is a partner
in. However, deputy secretary Gillis told the Estimates
hearing that one of the core lessons from the failed project
was the selection of a company that did not have a strong
history in certified ground based links to the WGS system.
“So, in hindsight, it was a poor selection,” he said.
Following questioning from South Australian Labor senator
Alex Gallacher, Gillis said that the west coast installation
had now been completed but the requirement for the east
coast portion of the project had been terminated.
“There is another project that will take on that capability,
and we have now sought, through a settlement deed, a full
recovery of those costs from BAE. That's been finalised,” he
said.
The project to take on the capability in the east will be
lead by Northrop Grumman Australia in partnership with Optus
and ViaSat and was announced in July last year. Under the
$223 million contract, Northrop Grumman will build a new
satellite ground station at the Kapooka army base just
outside of Wagga Wagga in NSW.
Meanwhile, details of the compensation deal between Defence
and BAE have not been made public. A spokesperson for BAE
Systems Australia told Space & Satellite AU that late last
year the company had received final acceptance for the
Satellite Ground Station – West and that BAE Systems is now
supporting the new ground station in Geraldton. BAE is also
continuing to support the Defence ground station at HMAS
Harman under a five-year support contract. Geoff Long,
Commsday